Cement Grinding Line for a Building Materials Plant in Tashkent

A long-established building materials manufacturer in Tashkent, a major industrial hub in Uzbekistan, faced a significant operational challenge. For years, they had relied on a traditional jet mill to produce high-value ultra-fine cement. While effective, the jet mill was energy-intensive and leading to prohibitively high production costs. This severely impacted their profit margins and hindered their competitive edge in the growing Central Asian market. The management team initiated a search for a more efficient and cost-effective cement grinding solution.

Their global search for reliable equipment led them to EPIC. The company’s strong technical expertise and proven track record in the field of fine powder processing stood out. Intrigued by the potential for significant cost savings, the plant’s engineers decided that a firsthand evaluation was necessary. A delegation visited EPIC’s factory in China for a detailed inspection and technical discussions.

During the visit, the client observed EPIC’s grinding systems in operation and engaged in in-depth conversations with the engineering team. They were particularly impressed by EPIC’s robust design philosophy, comprehensive project management experience, and the energy-efficient technology on display. The visit successfully addressed all their concerns regarding performance, maintenance, and final product consistency. The client concluded that EPIC possessed the deep industry knowledge and technical strength they required, making them the partner of choice.
Consequently, a contract was signed for EPIC to design and install a complete ultra-fine cement grinding production line.

The new production line has since been successfully commissioned, seamlessly replacing the old, costly jet mill. It consistently delivers the required product quality at a substantially lower operational cost, boosting the plant’s profitability and solidifying its position as a leading building materials supplier in the region.

Key Project Parameters:

Raw Material: Ultra-fine Cement

Required Capacity: 600 kg/h

Product Fineness: D90: 7.5μm